Framing is complete including Val's dormer and all interior walls. Progress will now appear to slow, as the fun stuff is done.
|
Val's Dormer on right |
Val will have a nice set of large windows looking to the front yard.
There will be 2 closets for the Master Bedroom. One that opens into the room.
|
That's it on the left with 2 double doors. |
The 2nd closet is in the dressing area that also serves as a hallway to get to the office from the Master Bedroom.
|
The 2nd closet would be on the left here. |
They started roughing in the ductwork today and should finish tomorrow.
We decided to move the air handler out of some spare space in the corner of a dormer to the small attic space. This will make running the ducting a lot easier. We just have to make sure that we can get up there to perform maintenance (i.e. replace filters).
|
Air Handler in overhead |
|
Ducting in Master Bedroom |
Along with completing the ducting, the paper should be installed on the roof tomorrow with the shingles going on early next week.