Tuesday, November 2, 2010

Insulation & Chimneys

We have had about a 1 week delay waiting for a mechanical permit.  Before the delay we got most of the insulation in and the chimneys got extended.  I also had a request for a current shot of the front and back.

I think the bricklayer did a good job matching the existing brick and they also added a little pizazz to the top.


We have most of the insulation in.  The walls and dormer ceilings are all done.  Flat ceiling areas will be blown in after the drywall is installed.  We needed the mechanical permit and inspection before putting up drywall.  The permit and inspection is all taken care of, so drywall begins tomorrow.

Val's Dormer

We have a really nice view out of our Master Bedroom window overlooking the lake.


Next...where did the kitchen go?